Factory Acceptance Test (FAT): Steps, Checklist, FAT vs SAT
A factory acceptance test (FAT) is a supplier-run test of finished equipment at the supplier’s own site, held before shipment against written acceptance criteria that the buyer has agreed. The factory acceptance test checks build quality, control logic, interlocks and performance in a controlled setting, and it ends in a signed acceptance document with a punch list of open items. A site acceptance test (SAT) then repeats the question after installation, using the buyer’s own utilities, interfaces and product. Five parts define a FAT: procedure, protocol, checklist, attendees and the limits of what a pass proves. Plant engineers and project managers at Malaysian manufacturers settle those five before DNC Automation or any other integrator ships an end-of-line packaging or weighing line to their facility.
What Is a Factory Acceptance Test?
A factory acceptance test is a formal test of finished equipment at the supplier’s factory, run before shipment to confirm that the machine meets the buyer’s specification. An equipment distributor describes the FAT as a series of tests and inspections by the manufacturer or supplier against specified requirements, design criteria and functionality. A third-party inspection firm adds that the test runs the actual machine through power-up, functional cycles, interlocks and performance under load, where a standard product inspection checks a sample against a data sheet. A control-panel builder adds that the test places the equipment in a modelled operating environment that mimics the conditions it will meet in service.
A passed factory acceptance test ends in a signed acceptance document. That signature usually releases the shipment and, in many contracts, a payment milestone. No regulation requires a FAT, but the supply contract often does, according to the same inspection firm.
The factory acceptance test is standard for capital equipment: automation lines, robotic work cells, control panels, test stands, packaging and assembly equipment. For single components, a pre-shipment inspection is the usual checkpoint instead.
Buyers insist on the FAT for a cost reason, so the next section sets out that reason.
Why Do Buyers Run a FAT Before Equipment Ships?
Buyers run a factory acceptance test before shipment because a defect found at the supplier’s factory costs less to fix than the same defect found on the buyer’s production floor. An independent consultancy cites the IBM Systems Sciences Institute for the figure that fixing a defect during implementation costs four to five times more than fixing it during design, and says the cost rises further when a problem first appears on site.
The cost of skipping a FAT sits in the logistics. A wiring error, a software bug or an undersized component found after installation means downtime, a technician flight and a delayed production start, on top of the original defect, according to a third-party inspection firm. At the factory, the supplier’s engineers, spare parts and tools already stand next to the equipment.
An equipment distributor lists four costs of skipping the FAT, each of which the buyer pays later:
- delays during installation
- unexpected system failures
- rework and added costs
- hazards at startup
The supplier gains as well. Both parties can confirm that the equipment meets the contract specification, and the buyer’s team sees the machine running before it ships. A guide from an electrical services firm adds that the FAT is a natural moment to review the bill of materials, start-up spares and maintenance procedures with key people from both sides in the same room.
The FAT works only if its steps are fixed in advance, and the procedure comes next.
What Are the Steps of a FAT Procedure?
A factory acceptance test procedure runs in eight steps, from agreed acceptance criteria to punch list and sign-off. The sequence below follows a third-party inspection firm, and an equipment distributor’s three phases of planning, documentation and testing fold into steps one to three.
- Define acceptance criteria.Buyer and supplier agree what “pass” means: specifications, tolerances, cycle times and applicable standards.
- Supplier pre-test.The supplier runs its own dry run first, so the buyer does not spend the test day on obvious faults.
- Documentation review.The team checks drawings, wiring diagrams, the bill of materials, software version records and calibration certificates against what is installed.
- Visual and mechanical inspection.Build quality, components, labelling, guarding and workmanship are compared with the approved design.
- Functional and performance testing.The machine runs its full sequence: normal cycles, changeovers and any specified endurance runs.
- Safety systems testing.Emergency stops, interlocks and guards are tested by deliberately triggering fault conditions.
- Software and controls verification.HMI screens, alarms, fault handling and control logic are checked against the functional specification.
- Punch list and sign-off.Each deficiency gets an owner and a deadline, and both parties sign the acceptance document.
The distributor places the FAT plan in the bid phase. Its scope covers customer specifications, standards and drawings, and the buyer sees it from the start. The same guide requires every instrument that records test data to be within its calibration date before the test begins.
Step one of the factory acceptance test produces the document that every later step tests against, which makes the protocol the next subject.
How Does a FAT Protocol Define Pass and Fail?
A factory acceptance test protocol defines pass and fail in a written test plan that both parties agree before the test starts. Without it, pass and fail become a negotiation on the test floor instead of a documented outcome, according to a third-party inspection firm. A guide on stretch wrapper testing goes further and says the test plan belongs at the quotation stage, because a machine whose criteria were never specified cannot be assessed competently.
The table lists the five elements of a complete FAT protocol and the failure each one prevents.
| Protocol element | What it states | Failure it prevents |
| Test case list | One numbered case per functional requirement | A vague “the equipment runs correctly” |
| Pass/fail criteria | A measurable threshold per case: a cycle time, a tolerance, a fault-response time | Argument over what counted as success |
| Sequence and duration | The order of tests and the length of any load or endurance run | Skipped or shortened runs |
| Roles and sign-off authority | Who on each side may accept or reject a result on the spot | Decisions deferred until after shipment |
| Punch list and deviation procedure | How a failed test is logged, fixed and retested | Open items with no owner |
Completeness of the FAT protocol matters more than length, and DNC recommends writing it before the build starts, not the week of the test. The inspection firm reports a protocol in Mexico that fixed a cycle time but not a changeover time, so the gap surfaced only after installation. A protocol in Vietnam caught a hidden interlock bypass because it required fault conditions to be triggered, not only a normal cycle to be observed.
A FAT protocol lists the cases, and the FAT checklist groups them by equipment area.

How Does a FAT Protocol Define Pass and Fail?
Which Categories Does a FAT Checklist Cover on a Machine or Line?
A factory acceptance test checklist covers six categories of test case, so that a minor oversight does not become a major field delay. The table shows the categories used by the equipment distributor and the inspection firm, with a packaging-line example in the last column.
| Category | What the FAT verifies | Packaging-line example |
| Documentation | Drawings, wiring diagrams, bill of materials, software version and calibration records match the as-built machine | Software version on the controller equals the version in the record |
| Mechanical and structural | Frame, alignment, fasteners, welds, correct components | Guarding and pinch points reviewed |
| Electrical and controls | Wiring, labelling, grounding, signal paths to the PLC and HMI | Each sensor signal reaches the controller |
| Safety | Every e-stop, interlock and light curtain triggers a safe state | Guard door opened mid-cycle |
| Functional performance | Cycle time, throughput, accuracy, repeatability against the agreed figure | Filler dosing accuracy and speed |
| Software and HMI | Screens, alarms, fault handling, recipes, data logging | Alarm raised for a simulated fault |
A packaging-machine manufacturer’s FAT tests each function in every working mode: automatic, semi-automatic and degraded. Its filler tests check dosing accuracy and filling speed, its capper tests check torque control, and its labeller tests check label precision and speed. An independent consultancy warns against one checklist for every machine, because a mechanical skid needs pressure and dimensional tests while a control panel needs wiring and I/O signal tests.
A weighing station adds a category that generic FAT checklists lack: the weight reading itself. The checklist for a station built through weighing system integration lists each link of the weighing chain, from the load cell and indicator to the reject and the data record. A later section returns to that station.
The checklist says what a factory acceptance test checks; who watches it, and when, comes next.
Who Attends a FAT, and When Is It Scheduled?
A factory acceptance test (FAT) is attended by five roles and scheduled after final assembly, once the control software is stable. A third-party inspection firm names the roles:
- the buyer’s process or manufacturing engineer
- the buyer’s quality representative or a third-party inspector
- the supplier’s project engineer
- controls engineers from both sides, where the equipment has custom PLC programming
- the project manager who owns the punch list and sign-off
Operators belong in that room too. A stretch wrapper FAT guide advises sending the people who will “own the line”, not only engineers, and training those same people during the test.
The schedule has a window. Three markers open the window: assembled, wired and functionally complete equipment, finished supplier commissioning, and loaded HMI programming. A FAT held too early produces a test full of unresolved issues that say nothing about final performance. A FAT held too late leaves no time to fix problems without delaying shipment.
FAT duration ranges from a few hours for a single-station machine to several days for a multi-station line. Remote participation is common: manufacturers offer live video walkthroughs, real-time observation and remote sign-off, and a local third-party inspector performs the physical checks while the buyer’s team observes.
The FAT ends at the factory door, so the comparison with the test at the buyer’s door follows.
What Is the Difference Between FAT and SAT?
The difference between a factory acceptance test (FAT) and a site acceptance test (SAT) is where, when and what each test asks: a factory acceptance test asks whether the equipment works as built, and a site acceptance test asks whether it works here. The table sets the two tests side by side, using the terms of an inspection firm and a pharmaceutical validation consultancy.
| Aspect | Factory acceptance test (FAT) | Site acceptance test (SAT) |
| Location | Supplier’s factory | Buyer’s facility |
| Timing | Before shipment | After installation and integration |
| Conditions | Factory power, air and test fixtures; standalone | Real utilities, upstream and downstream equipment, production material |
| Typical findings | Build defects, wiring errors, software bugs, missing components | Integration conflicts, utility mismatches, environmental effects |
| Documentation | Very detailed | Much simpler |
| Outcome | Approval for dispatch | Clearance for commissioning |
Environment explains the split between FAT and SAT. A packaging-machine manufacturer builds and adjusts its machines in controlled workshop conditions of temperature, pressure, humidity and lighting, and at a site in another region or country some components behave differently. The pharmaceutical consultancy adds that real compressed air or steam utilities exist only at the site.
SAT is not a second FAT. A site acceptance test that repeats what the factory test already covered wastes time, according to a maintenance-software company’s list of common mistakes. Both tests also sit inside a wider process, and where that process begins explains the third term that buyers mix up with them.
How Does Commissioning Differ From FAT and SAT?
Commissioning differs from both tests in scope: FAT is a time-boxed event of hours to a few days, SAT is the acceptance checkpoint after installation, and commissioning is the wider process that brings the equipment to full production. It includes tuning process parameters, running production trial batches, calibrating to actual materials and training operators over days or weeks. A machine passes FAT, passes SAT and still needs commissioning before it runs at target rate. The summary below pulls the factory acceptance test back to its core claim.

How Does Commissioning Differ From FAT and
Summary: What Does a Factory Acceptance Test Establish Before Shipment?
A factory acceptance test establishes, before shipment, that finished equipment meets a written specification under supplier-controlled conditions. The eight-step procedure, the protocol with numbered pass/fail cases and the checklist by category turn that claim into a signed acceptance document. Attendance from both sides and a window after final assembly keep the result credible. SAT then asks the same equipment a different question on the buyer’s site. What the factory result still says once the machine has been crated, shipped and connected is the limit of the test, and the next section sets it.
Which FAT Results Carry Over to Site, and Which Must Be Proven Again?
A factory acceptance test (FAT) result carries over to site only for the conditions under which the test ran. DNC groups every test case into three transfer classes, according to what the factory conditions share with the site.
The table sets out the classes and the reason each FAT result holds or stops.
| Transfer class | Test cases | Why the factory result holds or stops |
| Carries over | Build and dimensions against drawings; documents against the as-built machine; control logic and alarm response; the function of each e-stop and interlock | The result belongs to the equipment, which the test fixed in place, so nothing about the site changes it unless the machine is altered |
| Must be re-proven at SAT | Utility connections; behaviour under site temperature and humidity; network and data connections; handoff to upstream and downstream equipment; instrument accuracy after transport | The factory supplied its own power, air and test fixtures, so only the site supplies the real ones |
| Provable only in production | Sustained performance on real product; operator routine; long-run stability | The test ran for hours or days, and only production runs the real material at the real rate |
Each row traces to a source. The pharmaceutical consultancy places utilities and environment at SAT, the packaging-machine manufacturer places adjustment of components at SAT, and the inspection firm places upstream and downstream equipment and real production material there. The manufacturer’s own SAT description closes the loop: it verifies the accuracy of critical instruments and, in its performance stage, that the line reaches specified performance under real production conditions.
The third class carries the most risk. A passed FAT on a substitute product proves the mechanism and says little about how the real product behaves on the line. A guide on stretch wrapper testing makes the same point: use the materials that will run in production, including the production film, because the film’s gauge and quality change how the equipment is set up and how it performs.
A passed FAT is evidence about a set of conditions, not a certificate about the line. The inspection firm states the consequence directly: passing FAT does not guarantee passing SAT.
That limit on a factory acceptance test matters most where the equipment produces a measurement, so the weighing line comes next.
How Is a FAT Run for a Weighing or End-of-Line Line?
A factory acceptance test (FAT) for a weighing or end-of-line packaging line tests the line’s measurement as well as each machine’s motion. None of the pages reviewed for this article mention weighing, a checkweigher or a load cell. They describe pumps, skids, control panels, fillers and cappers, and the weighing station falls between those categories.
DNC’s engineers specify and commission end-of-line packaging and weighing systems for Malaysian manufacturers. When they evaluate a packaging line, the first specification they anchor is the measurand at each station, and the FAT protocol inherits it. Six points shape the FAT of such a line.
- State the criterion as a measurand.A checkweigher weighs each pack in motion in fractions of a second, according to a checkweigher supplier, where a static check samples 15 of 6,000 packs (0.25%), according to a Mettler-Toledo Garvens specialist writing for IFSQN. The FAT criterion names the in-motion reading at line speed, not a static reference weight.
- Use production packs.The stretch wrapper guide’s rule on production materials applies here: the pack, the film and the carton that run on site are the ones on the test floor.
- Calibrate the reference.The distributor’s rule that recording instruments hold a current calibration extends to the reference masses used to test the weight reading.
- Trigger the reject.The reject verdict and the physical removal are separate events on separate conveyors, so a pack that drifts on transfer produces a logged rejection that never physically happened. The fault script forces an underweight and an overweight pack and confirms removal, which follows the inspection firm’s fault-triggering step. The guide on how a checkweigher works explains the weighing window, zones and reject that the script exercises.
- Name the approval route.Where the weight record supports declared-quantity compliance, the protocol names the framework: OIML R51, MID or FPV pre-packaging verification.
- Test the changeover.Cycle time at one format proves little. The protocol fixes changeover time for each format, because the Mexico example shows what an unspecified figure costs.
A line adds the handoff between stations. Running stations one at a time proves each machine. Running adjacent stations together on the test floor tests the handoff, and a tolerance mismatch found at commissioning is a rework event, not a settings change. For a conveyor and turnkey line, that makes the line-level FAT the cheapest place to find an interface error.
DNC’s weighbridge page states that each unit is fully factory assembled and performance tested before shipment, which shows the factory acceptance test principle at a different scale.
Standards give the FAT protocol its outside reference, and the last section covers them.

How Is a FAT Run for a Weighing or End-of-Line Line?
What Do FIT, SIT and IEC 62381 Add to FAT and SAT?
The factory acceptance test gains two companion stages in the standard IEC 62381: the integration tests FIT and SIT. The 2024 edition, published on 30 July 2024 as edition 3.0, covers the factory acceptance test, factory integration test, site acceptance test and site integration test for automation systems in the process industry. It replaces the 2012 edition, adds an optional FIT and replaces annex forms with activity checklists. IEC 62381 frames its activities as a guideline to adapt to the process, plant or equipment.
An independent consultancy describes FIT as the stage in which systems from different makers are tested together before shipment, for example a control system from one maker and a safety system from another. A certification body lists FAT, SIT, string and SAT services as separate offers, which shows how the market splits the integration work.
For a packaging or weighing line, IEC 62381 is a reference for the FAT, not a requirement. The inspection firm lists the references that protocols draw on for such equipment: ISO 9001 for the quality system behind the supplier’s testing, IEC 61508 for safety-related control functions such as e-stops and interlocks, and NFPA 79 for the electrical design of industrial machinery destined for US facilities. DNC’s guide to packaging line safety standards covers the safety frameworks for the line itself. Naming the standard in the protocol upfront avoids a last-minute dispute over what “compliant” means. Open questions about the factory acceptance test itself are answered in the FAQ that follows.
Frequently Asked Questions: What Do Buyers Ask About a FAT?
A factory acceptance test (FAT) raises five questions that buyers ask most often: duration, legal status, failure, the link to the site acceptance test, and who pays for travel and inspection.
How long does a factory acceptance test take?
A factory acceptance test takes a few hours for a single-station machine and several days for a multi-station line. Complexity and the number of test cases set the length, not the physical size of the equipment.
Is a FAT legally required?
A FAT is not legally required, but it is often written into the supply contract as a condition for shipment and payment release. That clause makes it binding between buyer and supplier.
What happens if equipment fails a FAT?
When equipment fails a FAT, the supplier corrects the deficiencies and repeats the affected tests, in full or only for the failed items, before sign-off and shipment. Each deficiency goes on the punch list with an owner and a deadline.
Does passing FAT guarantee passing SAT?
Passing FAT does not guarantee passing SAT. The factory test confirms that the equipment works standalone, and integration issues tied to site utilities, layout or neighbouring equipment can still surface at SAT.
Who pays for FAT travel and inspection?
Payment for FAT travel and inspection depends on the contract. Some buyers send their own engineers, and others hire a local third-party inspector at the supplier’s factory, which is often cheaper than flying an internal engineer abroad.